Click here for Adobe Acrobat version
********************************************************
NOTICE
********************************************************
This document was converted from a PDF version
Content from the original version of the document such as
headers, footers, footnotes, endnotes, graphics, and page numbers
will not show up in this text version.
All text attributes such as bold, italic, underlining, etc. from the
original document will not show up in this text version.
Features of the original document layout such as
columns, tables, line and letter spacing, pagination, and margins
will not be preserved in the text version.
If you need the complete document, download the
Microsoft Word or Adobe Acrobat version.
*****************************************************************
Federal Communications Commission DA 22-590
Before the
Federal Communications Commission
Washington, D.C. 20554
In the Matter of )
)
Liberty Mobile USVI, Inc. ) File No.: EB-SED-21-00033052
) CD Acct. No.: 202232100018
) FRN: 0004499034
)
)
ORDER
Adopted: June 2, 2022 Released: June 2, 2022
By the Acting Chief, Enforcement Bureau:
1. The Enforcement Bureau of the Federal Communications Commission has entered into a
Consent Decree to resolve its investigation into whether Liberty Mobile USVI, Inc. (Liberty) failed to
report in a timely manner to the Commission an outage it experienced on its wireless network on May 10,
2021, in St. Croix, U.S. Virgin Islands. The Commissions outage reporting rules require
communications providers to report certain disruptions to their networks to the Commission, providing
the Commission with the means to analyze trends in network disruptions, collaborate with providers to
address network vulnerabilities, and formulate policies to improve network resilience. To settle this
matter, Liberty admits that it violated the Commissions network outage reporting rules, agrees to pay a
$48,000 civil penalty, and agrees to implement a three-year compliance plan to ensure future compliance.
2. After reviewing the terms of the Consent Decree and evaluating the facts before us, we
find that the public interest would be served by adopting the Consent Decree and terminating the
referenced investigation regarding Libertys compliance with the Commissions network outage reporting
rules, including sections 4.9 and 4.11 of the Commissions rules.1
3. In the absence of material new evidence relating to this matter, we do not set for hearing
the question of Libertys basic qualifications to hold or obtain any Commission license or authorization.2
4. Accordingly, IT IS ORDERED that, pursuant to section 4(i) of the Act3 and the
authority delegated by sections 0.111 and 0.311 of the Commissions rules,4 the attached Consent Decree
IS ADOPTED and its terms incorporated by reference.
5. IT IS FURTHER ORDERED that the above-captioned matter IS TERMINATED.
1 47 CFR 4.9, 4.11.
2 See 47 CFR 1.93(b).
3 47 U.S.C. 154(i).
4 47 CFR 0.111, 0.311.
Federal Communications Commission DA 22-590
6. IT IS FURTHER ORDERED that a copy of this Order and Consent Decree shall be
sent by first class mail and certified mail, return receipt requested, to Carla Framil Ferran, General
Counsel, Liberty Mobile USVI, Inc., 279 Ponce De Leon Avenue, San Juan, Puerto Rico, 00918, and
to Danielle Frappier, Esq., Davis Wright Tremaine LLP, 1301 K St, NW, Suite 500 East, Washington,
DC 20005.
FEDERAL COMMUNICATIONS COMMISSION
Loyaan A. Egal
Acting Chief
Enforcement Bureau
2
Federal Communications Commission DA 22-590
Before the
Federal Communications Commission
Washington, D.C. 20554
In the Matter of )
)
Liberty Mobile USVI, Inc. ) File No.: EB-SED-21-00033052
) CD Acct. No.: 202232100018
) FRN: 0004499034
)
)
CONSENT DECREE
1. The Enforcement Bureau of the Federal Communications Commission and Liberty
Mobile USVI, Inc., by their authorized representatives, hereby enter into this Consent Decree for the
purpose of terminating the Enforcement Bureaus investigation into whether Liberty violated sections 4.9
and 4.11 of the Commissions rules in connection with a disruption to Libertys network that it failed to
report in a timely manner.1 To resolve this matter, Liberty admits that it violated the network outage
reporting requirements set forth in the Commissions rules, agrees to pay a $48,000 civil penalty, and
agrees to implement a three-year compliance plan to ensure future compliance.
I. DEFINITIONS
2. For the purposes of this Consent Decree, the following definitions shall apply:
(a) Act means the Communications Act of 1934, as amended.2
(b) Adopting Order means an order of the Bureau adopting the terms of this Consent
Decree without change, addition, deletion, or modification.
(c) Bureau means the Enforcement Bureau of the Federal Communications
Commission.
(d) CD Acct No. means account number 202232100018, associated with payment
obligations described in paragraph 19 of this Consent Decree.
(e) Commission and FCC mean the Federal Communications Commission and all
of its bureaus and offices.
(f) Communications Laws means collectively, the Act, the Rules, and the published
and promulgated orders and decisions of the Commission to which Liberty is subject
by virtue of its business activities, including but not limited to the Network Outage
Reporting Rules.
(g) Compliance Plan means the compliance obligations, program, and procedures
described in this Consent Decree at paragraph 14.
(h) Covered Employees means all employees and agents of Liberty who perform,
supervise, oversee, or manage the performance of, duties that relate to Libertys
responsibilities under the Communications Laws, including the Network Outage
Reporting Rules.
(i) Effective Date means the date by which both the Bureau and Liberty have signed
the Consent Decree and the Bureau has released an Adopting Order.
1 47 CFR 4.9, 4.11.
2 47 U.S.C. 151 et seq.
Federal Communications Commission DA 22-590
(j) Investigation means the investigation commenced by the Bureau in File No. EB-
SED-21-00033052 regarding whether Liberty violated the Network Outage
Reporting Rules.
(k) Liberty or Company means Liberty Mobile USVI, Inc. and its affiliates,
subsidiaries, predecessors-in-interest, and successors-in-interest.
(l) Network Outage Reporting Rules means part 4 of the Rules, including sections
4.9 and 4.11 of the Rules, and other Communications Laws governing the reporting
of network outages.
(m) Operating Procedures means the standard internal operating procedures and
compliance policies established by Liberty to implement the Compliance Plan.
(n) Parties means Liberty and the Bureau, each of which is a Party.
(o) Rules means the Commissions regulations found in Title 47 of the Code of
Federal Regulations.
II. BACKGROUND
3. Under section 4.9(e)(1) of the Rules,3 a wireless service provider must report to the
Commission outages of at least 30 minutes duration: (i) that is of a Mobile Switching Center; (ii) that
potentially affects at least 900,000 user minutes of either telephony and associated data service or paging
service;4 (iii) that affects at least 667 Optical Carrier-level 3 (OC3) minutes;5 (iv) that potentially affects
any special offices and facilities other than airports through direct service facility agreements;6 or (v) that
potentially affects a 911 special facility.7 Wireless service providers must report such outages
electronically to the Commission in three separate filings: (i) a notification (Notification) within 120
minutes of discovery; (ii) an Initial Communications Outage Report (Initial Report) within 72 hours of
discovery; and (iii) a Final Communications Outage Report (Final Report) within 30 days of discovery.8
The Notification, Initial Report, and Final Report must contain specific information regarding the outage,
services affected, and communications provider.9 These outage reporting rules, among other things,
3 47 CFR 4.9(e)(1).
4 User minutes are defined as [a]ssigned telephone number minutes . . . for telephony, including non-mobile
interconnected VoIP telephony, and for those paging networks in which each individual user is assigned a telephone
number or the mathematical result of multiplying the duration of an outage, expressed in minutes, by the number
of end users potentially affected by the outage, for all other forms of communications. 47 CFR 4.7(e).
5 OC3 minutes are defined as the mathematical result of multiplying the duration of an outage, expressed in
minutes, by the number of previously operating OC3 circuits or their equivalents that were affected by the outage.
Id. 4.7(d).
6 Special offices and facilities are entities enrolled in the Telecommunications Service Priority (TSP) Program at
Levels 1 and 2, and may include major military installations, key government facilities, nuclear power plants, and
certain airports. Id. 4.5(b).
7 An outage that potentially affects a 911 special facility occurs whenever: (1) there is a loss of communications to
Public Safety Answering Points (PSAPs) potentially affecting at least 900,000 user-minutes; (2) there is a loss of
911 call processing capabilities in one or more E-911 tandems/selective routers for at least 30 minutes duration; (3)
one or more end-office or mobile switching center switches or host/remote clusters is isolated from 911 service for
at least 30 minutes and potentially affects at least 900,000 user-minutes; or (4) there is a loss of ANI/ALI (associated
name and location information) and/or a failure of location determination equipment for at least 30 minutes and
potentially affecting at least 900,000 user-minutes. See id. 4.5(e).
8 See id. 4.9(e)(1), (4).
9 See id. 4.11.
2
Federal Communications Commission DA 22-590
enable the Commission to analyze trends in network disruptions, collaborate with providers to address
network vulnerabilities, and formulate policies to improve network resilience.10
4. Liberty is a wireless service provider.11 On May 10, 2021, Liberty experienced an outage
(Outage) on its wireless network in St. Croix, U.S. Virgin Islands.12 The Outage took place when a
contractor performing excavation work on behalf of a third party inadvertently cut a fiber optic cable.13
5. On May 17, 2021, Liberty provided the Commissions Public Safety and Homeland
Security Bureau (PSHSB) with details about the Outage.14 On May 19, 2021, after reviewing details
about the Outage provided by the Company, PSHSB advised Liberty that the Outage may be reportable
under the Rules and gave instructions on submitting reports in the Commissions Network Outage
Reporting System (NORS).15 Liberty then submitted a late Notification and a late Initial Report, both on
June 1, 2021.16 The Company timely submitted the Final Report in NORS on June 2, 2021.17 PSHSB
subsequently referred this matter to the Bureau for investigation.
6. On December 1, 2021, the Bureau issued a Letter of Inquiry (LOI) to the Company
directing it to submit a sworn written response to a series of questions relating to the Outage.18 Liberty
timely responded to the LOI on January 31, 2022.19 In its response to the LOI, Liberty acknowledged that
it holds the sole responsibility under the Network Outage Reporting Rules to file any required reports
with respect to its network and its subscribers.20
7. Liberty and the Bureau subsequently engaged in settlement negotiations. To settle this
matter, the Company and the Bureau enter into this Consent Decree and agree to the following terms and
conditions.
III. TERMS OF AGREEMENT
8. Adopting Order. The provisions of this Consent Decree shall be incorporated by the
Bureau in an Adopting Order.
9. Jurisdiction. Liberty agrees that the Bureau has jurisdiction over it and the matters
contained in this Consent Decree and has the authority to enter into and adopt this Consent Decree.
10 Amendments to Part 4 of the Commission's Rules Concerning Disruptions to Communications, Report and Order,
Further Notice of Proposed Rulemaking, and Order on Reconsideration, PS Docket Nos. 15-80, 11-82, 31 FCC Rcd
5817, 5820-21, para. 8 (2016).
11 Response to Letter of Inquiry, from Danielle Frappier, Davis Wright Tremaine LLP, Counsel to Liberty Mobile
USVI Inc., to Elizabeth Y. Mumaw, Chief, Spectrum Enforcement Division, FCC Enforcement Bureau, at 3,
Response to Inquiry 8 (Jan. 31, 2022) (on file in EB-SED-21-00033052) (LOI Response).
12 Id. at 4, Response to Inquiry 9(a).
13 Id.
14 E-mail from Jose Arias-Lopez, Director, RAN Construction, Liberty Mobile USVI Inc., to Michael Caiafa,
Telecommunications Specialist, Cybersecurity and Communications Reliability Division, FCC Public Safety and
Homeland Security Bureau (May 17, 2021, 11:34 EDT) (on file in EB-SED-21-00033052).
15 E-mail from Michael Caiafa, Telecommunications Specialist, Cybersecurity and Communications Reliability
Division, FCC Public Safety and Homeland Security Bureau, to Wanda Perez, Government Affairs Counsel, Liberty
Mobile USVI Inc. (May 19, 2021, 10:18 EDT) (on file in EB-SED-21-00033052).
16 See NORS Report File No. ON-00236818.
17 Id.
18 Letter of Inquiry from Elizabeth Y. Mumaw, Chief, Spectrum Enforcement Division, FCC Enforcement Bureau,
to Luis B. Mendez del Nido, Liberty Mobile USVI Inc. (Dec. 1, 2021) (on file in EB-SED-21-00033052).
19 See generally LOI Response.
20 LOI Response at 5, Response to Inquiry 9(c).
3
Federal Communications Commission DA 22-590
10. Effective Date; Violations. The Parties agree that this Consent Decree shall become
effective on the Effective Date as defined herein. As of the Effective Date, the Parties agree that this
Consent Decree shall have the same force and effect as any other order of the Commission.
11. Termination of Investigation. In express reliance on the covenants and representations
in this Consent Decree and to avoid further expenditure of public resources, the Bureau agrees to
terminate the Investigation. In consideration for the termination of the Investigation, Liberty agrees to the
terms, conditions, and procedures contained herein. The Bureau further agrees that, in the absence of new
material evidence, it will not use the facts developed in the Investigation through the Effective Date, or
the existence of this Consent Decree, to institute any new proceeding on its own motion against Liberty
concerning the matters that were the subject of the Investigation, or to set for hearing the question of
Libertys basic qualifications to be a Commission licensee or hold Commission licenses or authorizations
based on the matters that were the subject of the Investigation.21
12. Admission of Liability. Liberty admits for the purpose of this Consent Decree and for
Commission civil enforcement purposes, and in express reliance on the provisions of paragraph 11 herein,
that its actions described in paragraphs 4 and 5 violated the Network Outage Reporting Rules.
13. Compliance Officer. Within thirty (30) calendar days after the Effective Date, Liberty
shall designate a senior corporate manager with the requisite corporate and organizational authority to
serve as a Compliance Officer and to discharge the duties set forth below. The person designated as the
Compliance Officer shall be responsible for developing, implementing, and administering the Compliance
Plan and ensuring that Liberty complies with the terms and conditions of the Compliance Plan and this
Consent Decree. In addition to the general knowledge of the Communications Laws necessary to
discharge his or her duties under this Consent Decree, the Compliance Officer shall have specific
knowledge of the Network Outage Reporting Rules prior to assuming his/her duties.
14. Compliance Plan. For purposes of settling the matters set forth herein, Liberty agrees
that it shall, within sixty (60) calendar days after the Effective Date, develop and implement a
Compliance Plan designed to ensure future compliance with the Network Outage Reporting Rules and
with the terms and conditions of this Consent Decree. With respect to the Network Outage Reporting
Rules, Liberty will implement, at a minimum, the following procedures:
(a) Operating Procedures. Within thirty (30) calendar days after the Effective Date,
Liberty shall establish Operating Procedures that all Covered Employees must
follow to help ensure Libertys compliance with the Network Outage Reporting
Rules. Libertys Operating Procedures shall include internal procedures and policies
specifically designed to ensure that Liberty performs its own determinations of
whether a network outage is reportable and reports outages in a timely manner
pursuant to section 4.9 of the Rules and other applicable Rules. Liberty shall also
develop a Compliance Checklist that describes the steps that a Covered Employee
must follow to ensure compliance with the Network Outage Reporting Rules.
(b) Compliance Manual. Within sixty (60) calendar days after the Effective Date, the
Compliance Officer shall develop and distribute a Compliance Manual to all
Covered Employees. The Compliance Manual shall explain the Network Outage
Reporting Rules and set forth the Operating Procedures that Covered Employees
shall follow to help ensure Libertys compliance with the Network Outage
Reporting Rules. Liberty shall periodically review and revise the Compliance
Manual as necessary to ensure that the information set forth therein remains current
and accurate. Liberty shall distribute any revisions to the Compliance Manual
promptly to all Covered Employees.
(c) Compliance Training Program. Liberty shall establish and implement a
Compliance Training Program on compliance with the Network Outage Reporting
21 See 47 CFR 1.93(b).
4
Federal Communications Commission DA 22-590
Rules and the Operating Procedures. As part of the Compliance Training Program,
Covered Employees shall be advised of Libertys obligation to report any
noncompliance with the Network Outage Reporting Rules under paragraph 15 of
this Consent Decree and shall be instructed on how to disclose noncompliance to the
Compliance Officer. All Covered Employees shall be trained pursuant to the
Compliance Training Program within sixty (60) calendar days after the Effective
Date, except that any person who becomes a Covered Employee at any time after the
initial Compliance Training Program shall be trained within thirty (30) calendar
days after the date such person becomes a Covered Employee. Liberty shall repeat
compliance training on an annual basis, and shall periodically review and revise the
Compliance Training Program as necessary to ensure that it remains current and
complete and to enhance its effectiveness.
15. Reporting Noncompliance. Liberty shall report any noncompliance with the Network
Outage Reporting Rules and with the terms and conditions of this Consent Decree within fifteen (15)
calendar days after discovery of such noncompliance. Such reports shall include a detailed explanation
of: (i) each instance of noncompliance; (ii) the steps that Liberty has taken or will take to remedy such
noncompliance; (iii) the schedule on which such remedial actions will be taken; and (iv) the steps that
Liberty has taken or will take to prevent the recurrence of any such noncompliance. All reports of
noncompliance shall be submitted to EB-SED-Response@fcc.gov, with a copy submitted electronically
to mark.desantis@fcc.gov.
16. Compliance Reports. Liberty shall file compliance reports with the Commission ninety
(90) calendar days after the Effective Date, twelve (12) months after the Effective Date, twenty-four (24)
months after the Effective Date, and thirty-six (36) months after the Effective Date.
(a) Each Compliance Report shall include a detailed description of Libertys efforts
during the relevant period to comply with the terms and conditions of this Consent
Decree and the Network Outage Reporting Rules. In addition, each Compliance
Report shall include a certification by the Compliance Officer, as an agent of and on
behalf of Liberty, stating that the Compliance Officer has personal knowledge that
Liberty: (i) has established and implemented the Compliance Plan; (ii) has utilized
the Operating Procedures since the implementation of the Compliance Plan; and (iii)
is not aware of any instances of noncompliance with the terms and conditions of this
Consent Decree, including the reporting obligations set forth in paragraph 15 of this
Consent Decree.
(b) The Compliance Officers certification shall be accompanied by a statement
explaining the basis for such certification and shall comply with section 1.16 of the
Rules and be subscribed to as true under penalty of perjury in substantially the form
set forth therein.22
(c) If the Compliance Officer cannot provide the requisite certification, the Compliance
Officer, as an agent of and on behalf of Liberty, shall provide the Commission with
a detailed explanation of the reason(s) why and describe fully: (i) each instance of
noncompliance; (ii) the steps that Liberty has taken or will take to remedy such
noncompliance, including the schedule on which proposed remedial actions will be
taken; and (iii) the steps that Liberty has taken or will take to prevent the recurrence
of any such noncompliance, including the schedule on which such preventive action
will be taken.
(d) All Compliance Reports shall be submitted to EB-SED-Response@fcc.gov, with a
copy submitted electronically to mark.desantis@fcc.gov.
22 47 CFR 1.16.
5
Federal Communications Commission DA 22-590
17. Termination Date. Unless stated otherwise, the requirements set forth in paragraphs 13
through 16 through of this Consent Decree shall expire thirty-six (36) months after the Effective Date.
18. Section 208 Complaints; Subsequent Investigations. Nothing in this Consent Decree
shall prevent the Commission or its delegated authority from adjudicating complaints filed pursuant to
section 208 of the Act23 against Liberty or its affiliates for alleged violations of the Act, or for any other
type of alleged misconduct, regardless of when such misconduct took place. The Commissions
adjudication of any such complaint will be based solely on the record developed in that proceeding.
Except as expressly provided in this Consent Decree, this Consent Decree shall not prevent the
Commission from investigating new evidence of noncompliance by Liberty with the Communications
Laws.
19. Civil Penalty. Liberty will pay a civil penalty to the United States Treasury in the
amount of Forty Eight Thousand Dollars ($48,000) within thirty (30) calendar days of the Effective Date.
Liberty acknowledges and agrees that upon execution of this Consent Decree, the Civil Penalty shall
become a Claim or Debt as defined in 31 U.S.C. 3701(b)(1).24 Upon an Event of Default, all
procedures for collection as permitted by law may, at the Commissions discretion, be initiated. Liberty
shall send electronic notification of payment to EB-SED-Response@fcc.gov, with a copy to
mark.desantis@fcc.gov on the date said payment is made. Payment of the Civil Penalty must be made by
credit card, ACH (Automated Clearing House) debit from a bank account, or by wire transfer using the
Commissions Registration System (the Commissions FRN Management and Financial system).25 The
Commission no longer accepts Civil Penalty payments by check or money order. Below are instructions
that payors should follow based on the form of payment selected:26
Payment by wire transfer must be made to ABA Number 021030004, receiving bank
TREAS/NYC, and Account Number 27000001. A completed Form 159 must be faxed to the
Federal Communications Commission at 202-418-2843 or e-mailed to
RROGWireFaxes@fcc.gov on the same business day the wire transfer is initiated.27 Failure to
provide all required information in Form 159 may result in payment not being recognized as
having been received. When completing FCC Form 159, enter the Account Number in block
number 23A (call sign/other ID), enter the letters FORF in block number 24A (payment type
code), and enter in block number 11 the FRN(s) captioned above (Payor FRN).28 For additional
detail and wire transfer instructions, go to https://www.fcc.gov/licensing-databases/fees/wire-
transfer.
Payment by credit card must be made by using the Commissions Registration System (CORES)
at https://apps.fcc.gov/cores/userLogin.do. To pay by credit card, log-in using the FCC
Username associated to the FRN captioned above. If payment must be split across FRNs,
complete this process for each FRN. Next, select Manage Existing FRNs | FRN Financial | Bills
& Fees from the CORES Menu, then select FRN Financial and the view/make payments option
next to the FRN. Select the Open Bills tab and find the bill number associated with the CD
Acct. No. The bill number is the CD Acct. No. with the first two digits excluded (e.g., CD
1912345678 would be associated with FCC Bill Number 12345678). After selecting the bill for
payment, choose the Pay by Credit Card option. Please note that there is a $24,999.99 limit on
credit card transactions.
23 47 U.S.C. 208.
24 Debt Collection Improvement Act of 1996, Pub. L. No. 104-134, 110 Stat. 1321, 1358 (Apr. 26, 1996).
25 Payments made using CORES do not require the submission of an FCC Form 159.
26 For questions regarding payment procedures, please contact the Financial Operations Group Help Desk by phone
at 1-877-480-3201 (option #6), or by e-mail at ARINQUIRIES@fcc.gov.
27 FCC Form 159 is accessible at https://www.fcc.gov/licensing-databases/fees/fcc-remittance-advice-form-159.
28 Instructions for completing the form may be obtained at http://www.fcc.gov/Forms/Form159/159.pdf.
6
Federal Communications Commission DA 22-590
Payment by ACH must be made by using the Commissions Registration System (CORES) at
https://apps.fcc.gov/cores/paymentFrnLogin.do. To pay by ACH, log in using the FCC
Username associated to the FRN captioned above. If payment must be split across FRNs,
complete this process for each FRN. Next, select Manage Existing FRNs | FRN Financial | Bills
& Fees on the CORES Menu, then select FRN Financial and the view/make payments option
next to the FRN. Select the Open Bills tab and find the bill number associated with the CD
Acct. No. The bill number is the CD Acct. No. with the first two digits excluded (e.g., CD
1912345678 would be associated with FCC Bill Number 12345678). Finally, choose the Pay
from Bank Account option. Please contact the appropriate financial institution to confirm the
correct Routing Number and the correct account number from which payment will be made and
verify with that financial institution that the designated account has authorization to accept ACH
transactions.
20. Event of Default. Liberty agrees that an Event of Default shall occur upon the failure by
Liberty to pay the full amount of the Civil Penalty on or before the due date specified in this Consent
Decree.
21. Interest, Charges for Collection, and Acceleration of Maturity Date. After an Event
of Default has occurred under this Consent Decree, the then unpaid amount of the Civil Penalty shall
accrue interest, computed using the U.S. Prime Rate in effect on the date of the Event of Default plus
4.75%, from the date of the Event of Default until payment in full. Upon an Event of Default, the then
unpaid amount of the Civil Penalty, together with interest, any penalties permitted and/or required by the
law, including but not limited to 31 U.S.C. 3717 and administrative charges, plus the costs of collection,
litigation, and attorneys fees, shall become immediately due and payable, without notice, presentment,
demand, protest, or notice of protest of any kind, all of which are waived by Liberty.
22. Waivers. As of the Effective Date, Liberty waives any and all rights it may have to seek
administrative or judicial reconsideration, review, appeal or stay, or to otherwise challenge or contest the
validity of this Consent Decree and the Adopting Order. Liberty shall retain the right to challenge
Commission interpretation of the Consent Decree or any terms contained herein. If either Party (or the
United States on behalf of the Commission) brings a judicial action to enforce the terms of the Consent
Decree or the Adopting Order, neither Liberty nor the Commission shall contest the validity of the
Consent Decree or the Adopting Order, and Liberty shall waive any statutory right to a trial de novo.
Liberty hereby agrees to waive any claims it may otherwise have under the Equal Access to Justice Act29
relating to the matters addressed in this Consent Decree.
23. Severability. The Parties agree that if any of the provisions of the Consent Decree shall
be held unenforceable by any court of competent jurisdiction, such unenforceability shall not render
unenforceable the entire Consent Decree, but rather the entire Consent Decree shall be construed as if not
containing the particular unenforceable provision or provisions, and the rights and obligations of the
Parties shall be construed and enforced accordingly.
24. Invalidity. In the event that this Consent Decree in its entirety is rendered invalid by any
court of competent jurisdiction, it shall become null and void and may not be used in any manner in any
legal proceeding.
25. Subsequent Rule or Order. The Parties agree that if any provision of the Consent
Decree conflicts with any subsequent Rule or order adopted by the Commission (except an order
specifically intended to revise the terms of this Consent Decree to which Liberty does not expressly
consent) that provision will be superseded by such Rule or order.
26. Successors and Assigns. Liberty agrees that the provisions of this Consent Decree shall
be binding on its successors, assigns, and transferees.
29 See 5 U.S.C. 504; 47 CFR 1.15011.1530.
7
Federal Communications Commission DA 22-590
27. Final Settlement. The Parties agree and acknowledge that this Consent Decree shall
constitute a final settlement between the Parties with respect to the Investigation.
28. Modifications. This Consent Decree cannot be modified without the advance written
consent of both Parties.
29. Paragraph Headings. The headings of the paragraphs in this Consent Decree are
inserted for convenience only and are not intended to affect the meaning or interpretation of this Consent
Decree.
30. Authorized Representative. Each Party represents and warrants to the other that it has
full power and authority to enter into this Consent Decree. Each person signing this Consent Decree on
behalf of a Party hereby represents that he or she is fully authorized by the Party to execute this Consent
Decree and to bind the Party to its terms and conditions.
31. Counterparts. This Consent Decree may be signed in counterpart (including
electronically or by facsimile). Each counterpart, when executed and delivered, shall be an original, and
all of the counterparts together shall constitute one and the same fully executed instrument.
________________________________
Loyaan A. Egal
Acting Chief
Enforcement Bureau
________________________________
Date
________________________________
Carla Framil Ferran
General Counsel
Liberty Mobile USVI, Inc.
________________________________
Date
8