Click here for Adobe Acrobat version

******************************************************** 
                      NOTICE
********************************************************

This document was converted from a PDF version

Content from the original version of the document such as
headers, footers, footnotes, endnotes, graphics, and page numbers
will not show up in this text version.

All text attributes such as bold, italic, underlining, etc. from the
original document will not show up in this text version.

Features of the original document layout such as
columns, tables, line and letter spacing, pagination, and margins
will not be preserved in the text version.

If you need the complete document, download the
Microsoft Word or Adobe Acrobat version.

*****************************************************************



Federal Communications Commission DA 21-1365

Before the
Federal Communications Commission
Washington, D.C. 20554

In the Matter of )
)
Fort Myers Broadcasting Company ) File No.: EB-SED-21-00032162
) CD Acct. No.: 202232100009
) FRN: 0004078598
)
)

ORDER

Adopted: November 2, 2021 Released: November 2, 2021

By the Associate Chief, Enforcement Bureau:

1. The Enforcement Bureau of the Federal Communications Commission (Commission) has
entered into a Consent Decree to resolve its investigation into whether Fort Myers Broadcasting Company
(FMBC) began clearing land for a wireless telecommunications tower before completing the required
environmental review, as required by the Commission's environmental rules, including rules
implementing the National Environmental Policy Act of 1969 (NEPA).1
The Commission's rules ensure
applicants and licensees comply with environmental review and antenna structure registration procedure
requirements to assess whether proposed facilities may significantly affect the environment. To settle this
matter, FMBC admits that it violated the Commission's environmental and antenna structure rules, will
implement a compliance plan, and will pay a $20,000 civil penalty.
2. After reviewing the terms of the Consent Decree and evaluating the facts before us, we
find that the public interest would be served by adopting the Consent Decree and terminating the
referenced investigation regarding FMBC's compliance with environmental protection requirements
found in NEPA and in sections 1.1307 and 1.1312 of the Commission's rules,2 as well as the antenna
3
structure registration procedures found in section 17.4 of the Commission's rules.
3. In the absence of material new evidence relating to this matter, we do not set for hearing
4
the question of FMBC's basic qualifications to hold or obtain any Commission license or authorization.
5
4. Accordingly, IT IS ORDERED that, pursuant to section 4(i) of the Act and the
authority delegated by sections 0.111 and 0.311 of the Commission's rules,6 the attached Consent Decree
IS ADOPTED and its terms incorporated by reference.
5. IT IS FURTHER ORDERED that the above-captioned matter IS TERMINATED in
accordance with the terms of the attached Consent Decree.


1
See National Environmental Policy Act of 1969, Pub. L. No. 91 -190, 83 Stat. 852 (1970) (codified as amended at
42 U.S.C. S: 4321 et seq.) (NEPA).
2
Id.; 47 CFR S:S: 1.1307, 1.1312.
3
47 CFR S: 17.4.
4
See 47 CFR S: 1.93(b).
5
47 U.S.C. S: 154(i).
6
47 CFR S:S: 0.111, 0.311.

Federal Communications Commission DA 21-1365

6. IT IS FURTHER ORDERED that a copy of this Order and Consent Decree shall be
sent by e-mail to Mark Gilson, Assistant Secretary, Fort Myers Broadcasting Company,
mark.gilson@fmbcmail.com, and to Joseph A. Belisle, Esq., Belisle Law Firm, P.A.,
joe@belislelaw.com.

FEDERAL COMMUNICATIONS COMMISSION




Jeremy D. Marcus
Associate Chief
Enforcement Bureau

2
Federal Communications Commission DA 21-1365
Before the
Federal Communications Commission
Washington, D.C. 20554

In the Matter of )
) File No.: EB-SED-21-00032162
Fort Myers Broadcasting Company ) CD Acct. No.: 202232100009
) FRN: 0004078598
)
)
)

CONSENT DECREE

1. The Enforcement Bureau of the Federal Communications Commission andF ort Myers
Broadcasting Company (FMBC), by their authorized representatives, hereby enter into this Consent
Decree for the purpose of terminating the EnforcementB ureau's investigation into whether FMBC
violated sections 1.1307 and 1.1312 of the Commission's rules in connection with its construction
activities for a wireless telecommunications facility before completing the required environmental review.
To resolve this matter, FMBC admits that it violated the Commission's rules, will implement a
compliance plan, and will pay a $20,000 civil penalty.
I. DEFINITIONS
2. For the purposes of this Consent Decree, the following definitions shall apply:
1
(a) "Act" means the Communications Act of 1934, as amended.
(b) "Adopting Order" means an order of the Bureau adopting the terms of this Consent
Decree without change, addition, deletion, or modification.
(c) "Antenna Structure Registration (ASR) Rules" means sections 17.1-17.7 of the
2
Rules and other Communications Laws implementing procedures for antenna
structure registration and application.
(d) "Bureau" means the Enforcement Bureau of the Federal Communications
Commission.
(e) "CD Acct No." means account number 202232100009, associated with payment
obligations described in paragraph 17 of this Consent Decree .
(f) "Commission" and "FCC" mean the Federal Communications Commission and all
of its bureaus and offices.
(g) "Communications Laws" means collectively, the Act, the Rules, and the published
and promulgated orders and decisions of the Commission to which FMBC is subject
by virtue of its business activities, including but not limited to the Environmenta l
Rules and the ASR Rules.
(h) "Compliance Plan" means the compliance obligations, program, and procedures
described in this Consent Decree at paragraph 13.
(i) "Covered Employees" means all employees and agents of FMBC who perform,
supervise, oversee, or manage the performance of, duties that relate to FMB's C

1
47 U.S.C. S: 151 et seq.
2
47 CFR S: 17.1-17.7.

Federal Communications Commission DA 21-1365
responsibilities under the Communications Laws, including the Environmental and
ASR Rules.
(j) "Effective Date" means the date by which both the Bureau and FMBC have signed
the Consent Decreea nd the Bureau has released an Adopting Order.
3 and other
(k) "Environmental Rules" means sections 1.1301-1.1319 of the Rules
Communications Laws implementing the National Environmental Policy Act of
4
1969, as amended (NEPA).
(l) "FMBC or Company" means Fort Myers Broadcasting Company and its affiliates,
subsidiaries, predecessor-sin-interest, and successor-sin-interest.
(m) "Investigation" means the investigation commenced by the Bureau in EB-SED-21-
00032162 regarding whether FMBC violated the Environmental Rules and the ASR
5
Rules.
(n) "Operating Procedures" means the standard internal operating procedures and
compliance policies established by FMBC to implement the Compliance Plan.
(o) "Parties" means FMBC and the Bureau, each of which is a "Party."
(p) "Rules" means the Commission's regulations found in Title 47 of the Code of
Federal Regulations .
II. BACKGROUND
3. Under the Commission's Environmental Rules, applicants and licensees are required to
assess whether certain proposed facilities may significantly affect the environment, as definedec int ison
1.1307 of the Rules.6 Specifically, section 1.1307(a)(3) requires a licensee or applicant to prepare an
7
Environmental Assessment (EA) for facilities that may have a significant environmental effect .Pursuant
to section 1.1312, this obligation expressly applies to certain facilities for which no preconstruction
8
authorization is required, unless exempt. In considering actions that may have a significant
environmental effect, section 1.1307(a)(3) requires a licensee or applicant to consider several factors,
including, but not limited to, whether the proposed site mayaf fect listed threatened or endangered species
9
or designated critical habitats. Under the Commission's ASR Rules, the owner of any proposed or
existing antenna structure is required to follow the prescribed registration procedures set forth in section
10
17.4 of the Rules prior to construction or alteration. If an EA is required under section 1.1307, the ASR
11
applicant must include the EA with its submission.
4. FMBC is an established FCC licensee and provider of television and radio services
within the State of Florida. In July and August 2020, the licensee engaged a series of independent
contractors to perform the required environmental review, antenna structure registration procedures, and
construction for a proposed wireless communications tower within a designated critical habitat of the

3
47 CFR S:S: 1.1301 -1.1319.
4
National Environmental Policy Act of 1969 , Pub. L. No. 9-1190, 83 Stat. 852 (1970) (codified as amended at 42
U.S.C. S: 4321 et seq.) (NEPA).
5
LOI issued under File No. EB-SED-21-00031915 (on file in E-BSED-21-00032162).
6
47 CFR S: 1.1307.
7
47 CFR S: 1.1307(a)(3).
8
See 47 CFR S: 1.1312(a) , (e).
9
47 CFR S: 1.1307(a)(3).
10
47 CFR S: 17.4.
11
See 47 CFR S:S: 1.923(e), 17.4(c).
2
Federal Communications Commission DA 21-1365
endangered Florida bonneted bat in Punta Gorda, Florida (Punta Gorda Tower). During the ASR
application and environmental review process, FMBC admitted to preconstruction activities.12 In
November 2020, FMBC filed an ASR application and EA related to the Punta Gorda Tower depicting the
13
premature clearing.
5. The Wireless Telecommunication Bureau (WTB) referred the matter thoe E t nforcement
Bureau and the Enforcement Bureau's Spectrum Enforcement Division (SED) opened the Investigation.
SED issued a Letter of Inquiry to FMBC, directing it to submit a sworn written response to a series of
14
questions relating to its compliance with the Commission's Environmental and ASR Rules. FMBC
15
filed a response to the Letter of Inquiry on July 1, 2021 (LOI Response). In the LOI Response, FMBC
admits that it began construction by clearing vegetation in the tower site on or about August 3, 2020 ,
before preparing an EA and before applying for an ASR for the Punta Gorda Tower.16 Since commencing
the Investigation, WTB has concluded the environmental review and authorized construction of the Punta
Gorda Tower.17
6. FMBC violated the Environmental and ASR Rules by failing to complete the requisite
environmental review and antenna structure registration processes before initiating construction of the
Punta Gorda Tower. Specifically, it failed to initiate and complete the environmental review of whether
the proposed tower could have a significant effect on the environment or may affect listed threatened or
endangered species prior to clearing land within the critical habitat. The Bureau and FMBC entered into a
tolling agreement to toll the statute of limitations and negotiated the terms of the Consent Decree.
III. TERMS OF AGREEMENT
7. Adopting Order. The provisions of this Consent Decree shall be incorporated by the
Bureau in an Adopting Order.
8. Jurisdiction. FMBC agrees that the Bureau has jurisdiction over it and the matters
contained in this Consent Decree and has thea uthority to enter into and adopt this Consent Decree.
9. Effective Date; Viola tions. The Parties agree that this Consent Decree shall become
effective on the Effective Date as defined herein. As of the Effective Date, the Parties agree that this
Consent Decree shall have the same force and effect as any oth orerder of the Commission.

12
See E-mail from Joseph A. Belisle, Belisle Law Firm, Counsel for FMBC, to Erica Rosenberg, Assistant Chief,
Competition and Infrastructure Policy Division, FCC Wireless Commtuionnics Baureau (Jan. 27, 2021, 12:41 EDT)
(on file in E-BSED-21-00032162) .
13
See WTB, Online Systems, Antenna Structure Registration Application,
(last visited August 13, 2021)
https://wireless2. fcc.gov/UlsApp/AsrSearch/asrApplication.jsp?applKey=4665155
(ASR Application; s)ee also Environmental Assessme antt 8, 10, 56, 61-63, 74-76 (Appendix E at 1),
https://wireless2.fcc.gov/UlsEntry/attachments/attancthVmieewRD.jsp?applType=search&fileKey=1151043247&at
tachmentKey=20170007&applID=4642856&attchExt=pdf&attchLocDt=202011&applOrLicK (elay=stT visited
August 13, 2021).
14
See Letter of Inquiry from JoAnn Lucanik, Deputy Chief, Spectrum Enforcement Division, FCC Enforcement
Bureau to Joseph A. Belisle, Belisle Law Firm,n Cseol fuor FMBC (April 9, 2021) (on file in EB-SED-21-
00032162) (LOI).
15
See Response to Lettero f Inquiry, from Joseph A. Belisle, Belisle Law Firm, Counsel for FMBC, to JoAnn
Lucanik, Deputy Cihef, Spectrum Enforcement Division, FCC Enforcement Bu,re aat 2u3-25, Response to Question
20 (July 1, 2021) (on file in EB -SED-21-00032162) (LOI Response ).
16
See LOI Response to Question 21 at 5, 25-26.
17
On May 5, 2021, WTB issued a Finding of No Signifi cant Impact and granted the antenna structure registration on
May 7, 2021. See generally ASR Applicatio; nsee also LOI Response to Question 1at5 21-22. To offset potential
impacts to the environment caused by the premature clearing, FMBC voluntarily contributed to the Fish and
Wildlife Foundation of Florida's "Flor ida Bonneted Bat Fund" to address the loss of potential roost trees. See LOI
Response to Question 9 at 19-20.
3
Federal Communications Commission DA 21-1365
10. Termination of Investigation. In express reliance ont he covenants and representations
in this Consent Decree and to avoid further expenditure of public resources, the Bureau agrees to
terminate the Investigation. In consideration for the termination of the Investigation, FMBC agrees to the
terms, conditions, and procedures contained herein. The Bureau further agrees that i,n the absence of new
material evidence, i twill not use the facts developed in the Investigation through the Effective Date, or
the existence of this Consent Decree, to institute any new proceedingon i ts own motion against FMBC
concerning the matters that were the subject of the Investigation ,or to set for hearing the question of
FMBC's basic qualifications to be a Commission licensee or hold Commission licenses or authorizations
18
based on the matters that were the subject of the Investigation.
11. Admission of Liability. FMBC admits for the purpose of this Consent Decree and for
Commission civil enforcement purposes, and in express reliance on the provisions of paragraph 10h erein,
that its actions violated the Environmental Rules and the ASR Rules.
12. Compliance Officer. Within thirty (30) calendar days after the Effective Date, FMB C
shall designate a senior corporate manager with the requisite corporate and organizational authority to
serve as a Compliance Officer and to discharge the duties set forth below. The person designated as the
Compliance Officer shall be responsible for developing, implementing, and administering the Compliance
Plan and ensuring that FMBC complies with the terms and conditions of the Compliance Plan and this
Consent Decree. In addition to the general knowledge of the Communications Laws necessary to
discharge his or her duties under this Consent Decree, the Compliance Officer shall have specic fi
knowledge of the Environmental and ASR Rules prior to assuming his/her duties.
13. Compliance Plan. For purposes of settling the matters set forth herein, FMBC agrees
that it shall, within sixty (60) calendar days after the Effective Date, develop and implement a
Compliance Plan designed to ensure future compliance with the Communications Laws and with the
terms and conditions of this Consent Decree. With respect to the Environmental and ASR Rules, FMBC
will implement, at a minimum, the following procedures:
(a) Operating Procedures. Within thirty (30) calendar days after the Effective Date,
FMBC shall establish Operating Procedures that all Covered Employees must
follow to help ensure FMBC's compliance with the Environmental and ASR Rules.
FMBC's Operating Procedures shall include internal procedures and policies
specifically designed to ensure that all environmental review and ASR obligations
are fully satisfied prior to commencing construction on any proposed wireless
facilities. FMBC shall also develop a Compliance Checklist that describes the steps
that a Covered Employee must follow to ensure compliance with the Environmental
and ASR Rules.
(b) Compliance Manual. Within sixty (60) calendar days after the Effective Date, the
Compliance Officer shall develop and distribute a Compliance Manual to all
Covered Employees. The Compliance Manual shall explain the Environmental and
ASR Rules and set forth the Operating Procedures that Covered Employees shall
follow to help ensure FMBC's compliance with the Environmental and ASR Rules.
FMBC shall periodically review and revise the Compliance Manual as necessary to
ensure that the information set forth therein remains current and accurate. FMB C
shall distribute any revisions to the Compliance Manual promptly to all Covered
Employees.
(c) Compliance Training Program. FMBC shall establish and implement a
Compliance Training Program on compliance with the Environmental and ASR
Rules and the Operating Procedures. As part of the Compliance Training Program,
Covered Employees shall be advised of FMBC's obligation to report any
noncompliance with the Environmental and ASR Rules under paragraph 14 of this

18
See 47 CFR S: 1.93(b).
4
Federal Communications Commission DA 21-1365
Consent Decree and shall be instructed on how to disclose noncompliance to the
Compliance Officer. All Covered Employees shall be trained pursuant to the
Compliance Training Program within sixty (60) calendar days after the Effective
Date, except that any person who becomes a Covered Employee at any time after the
initial Compliance Training Program shall be trained within thirty (30) calendar
days after the date such person becomes a Covered Employee. FMBC shall repeat
compliance training on an annual basis, and shall periodically review andr evise the
Compliance Training Program as necessary to ensure that it remains current and
complete and to enhance its effectivenes s.
14. Reporting Noncompliance. FMBC shall report any noncompliance with the
Environmental and ASR Rules and with the terms and conditions of this Consent Decree within fifteen
(15) calendar days after discovery of such noncompliance. Such reports shall include a detailed
explanation of: (i) each instance of noncompliance; (ii) the steps that FMB haCs taken or will take to
remedy such noncompliance; (iii) the schedule on which such remedial actions will be taken; and (iv) the
steps that FMBC has taken or will take to prevent the recurrence of any such noncompliance. All reports
of noncompliance shall be submitted electronicallyt o the Chief, Spectrum Enforcement Division,
Enforcement Bureau, Federal Communications Commission, at EB-SED-Response@fcc.gov, with a copy
submitted electronically to Daniela Arregui at Daniela.Arregui@fcc.gov.
15. Compliance Reports. FMBC shall file compliance reports with the Commission ninety
(90) calendar days after the Effective Date, twelve (12) months after the Effective Date, twe-fnourty (24)
months after the Effective Date, and thirty-six (36) months after the Effective Date.
(a) Each Compliance Report shall include a detailed description of FMBC's efforts
during the relevant period to comply with the terms and conditions of this Consent
Decree and the Environmental and ASR Rules. In addition, each Compliance
Report shall include a certification by the Compliance Officer, as an agent of and on
behalf of FMBC, stating that the Compliance Officer has personal knowledge that
FMBC: (i) has established and implemented the Compliance Plan; (ii) has utilized
the Operating Procedures since the implementation of the Compliance Plan; and (iii)
is not aware of any instances of noncompliance with the terms and conditions of this
Consent Decree, including the reporting obligations set forth in paragraph 14 of this
Consent Decree.
(b) The Compliance Officer's certification shall be accompanied by a statement
explaining the basis for such certification and shall comply with section 1.16 of the
Rules and be subscribed to as true under penalty of perjury in substantially the form
19
set forth therein.
(c) If the Compliance Officer cannot provide the requisite certification, the Compliance
Officer, as an agent of and on behalf of FMBC, shall provide the Commission with a
detailed explanation of the reason(s) why and describe fully: (i) each instance of
noncompliance; (ii) the steps that FMBC has taken or will take to remedy such
noncompliance, including the schedule on which proposed remedial actions will be
taken; and (iii) the steps that FMBC has taken or will take to prevent the recurrence
of any such noncompliance, including the schedule on which such preventive action
will be taken.
(d) All Compliance Reports shall be submitted electronically to the Chief, Spectrum
Enforcement Division, Enforcement Bureau, Federal Communications Commission,
at EB-SED-Response@fcc.gov, with a copy submitted electronically to Daniela
Arregui at Daniela.Arregui@fcc.gov.

19
47 CFR S: 1.16.
5
Federal Communications Commission DA 21-1365
16. Termination Date. Unless stated otherwise, the requiemr ents set forth in paragraphs 12
through 15 of this Consent Decree shall expire thirty-six (36) months after the Effective Date.
17. Civil Penalty. FMBC will pay a civil penalty to the United States Treasury in the
amount of twenty thousand dollars ($20,000) within thirty (30) calendar days of the Effective Date.
FMBC acknowledges and agrees that upon execution of this Consent Decree, the Civil Penalty shall
20
become a "Claim" or "Debt" as defined in 31 U.S.C. S:3701( b)(1). Upon an Event of Default, all
procedures for collection as permitted by law may, at the Commission's discretion, be initiated. FMBC
EB-SED-
shall send electronic notification of payment to Daniela.Arregui@fcc.gov and
Response@fcc.gov on the date said payment is made. Payment of the Civil Penalty must be made by
credit card, ACH (Automated Clearing House) debit from a bank account using the Commission's Fee
21
Filer (the Commission's online payment system), or by wire transfer. The Commission no longer
accepts Civil Penalty payments by check or money order. Below are instructions that payors should
22
follow based on the form of payment selected:
x Payment by wire transfer must be made to ABA Number 021030004, receiving bank
TREAS/NYC, and Account Number 27000001. A completed Form 159 must be faxed to the
Federal Communications Commission at 202-418-2843 or e-mailed to
RROGWireFaxes@fcc.gov on the same business day the wire transfer is initiated. Failure to
provide all required information in Form 159 may result in payment not being recognized as
having been received. When completing FCC Form 159, enter the Account Number in block
number 23A (call sign/other ID), enter the letters "FORF" in block number 24A (payment
23 For
type code), and enter in block number 11 the FRN(s) captioned above (Payor FRN.)
https://www.fcc.gov/licensing -
additional detail and wire transfer instruct ions, go to
databases/fees/wire-transfer.
x Payment by credit card must be made by using the Commission'sF ee Filer website at
https://apps.fcc.gov/FeeFiler/login.cfm . To pay by credit card, log-in using the FRN
captioned above. If payment must be split across FRNs, complete this process for each FRN.
Next, select "Pay bills" on the Fee Filer Menu, and select the bill number associated with the
CD Acct. No. - the bill number is the CD Acct. No. with the first two digits excluded - and
then choose the "Pay by Credit Card" option. IMPORTANT NOTE: there is a $24,999.99
limit on credit card transactions .
x Payment by ACH must be made by using the Commission's Fee Filer website at
https://apps.fcc.gov/FeeFiler/login.cfm . To pay by ACH, log in using the FRN captioned
above. If payment must be split across FRNs, complete this process for each FRN.N ext,
select "Pay bills" on the Fee Filer Menu and then select the bill number associated w tithhe
CD Acct. No. - the bill number is the CD Acct. No. with the first two digits excluded (e.g.,
NAL 1912345678 = FCC bill Number 12345678) -a nd choose the "Pay from Bank
Account" option. Please contact the appropriate financial institution to confirm the correct
Routing Number and the correct account number from which payment will be made and
verify with that financial institution that the designated account has authorization to accept
ACH transactions.
18. Event of Default. FMBC agrees that an Event of Default shall occur upon the failure by
FMBC to pay the full amount of the Civil Penalty on or before the due date specified in this Consent
Decree.

20
Debt Collection Improvem ent Act of 1996, Pub. L. No. 104 -134, 110 Stat. 1321, 1358 (Apr. 26, 1996).
21
Payments made using the Commission's Fee Filer system do not require the submission of an FCC Form 159.
22
For questions regarding payment procedures, please contact the Financial Operations Group Help Desk by phone
at 1-877-480-3201 (option #6,) or by e-mail at ARINQUIRIES@fcc.go. v
23
Instructions for completing the form may be obtained at http://www.fcc.gov/Forms/Form159/159.pd.f
6
Federal Communications Commission DA 21-1365
19. Interest, Charges for Collection, and Acceleration of Maturity Date. After an Event
of Default has occurred under this Consent Decree, the then unpaid amount of the Civil Penaltys hall
accrue interest, computed using the U.S. Prime Rate in effect on the date of the Event of Default plus
4.75%, from the date of the Event of Default until payment in full. Upon an Event of Default, the then
unpaid amount of the Civil Penalty, together with interest, any penalties permitted and/or required by the
law, including but not limited to 31 U.S.C. S: 3717 and administrative charges, plus the costs of collection,
litigation, and attorneys' fees, shall become immediately due and payable, without notice, presentment,
demand, protest, or notice of protest of any kind, all of which are waived by FMBC.
20. Waivers. As of the Effective Date, FMBC waives any and all rights it may have to seek
administrative or judicial reconsideration, review, appeal or stay, or to otherwise challenge or contest the
validity of this Consent Decree and the Adopting Order. FMBC shall retain the right to challenge
Commission interpretation of the Consent Decree or any terms contained herein. If either Party (or the
United States on behalf of the Commission) brings a judicial action to enforce the terms of the Consent
Decree or the Adopting Order, neither FMBC nor the Commission shall contest the validity of the
Consent Decree or the Adopting Order, and FMBC shall waive any statutory right to a trial de novo.
24
FMBC hereby agrees to waive any claims it may otherwise have under the Equal Access to Justice Act
relating to the matters addressed in this Consent Decree.
21. Severability. The Parties agree that if any of the provisions of the Consent Decreesh all
be held unenforceable by any court of competent jurisdiction, such unenforceability shall not render
unenforceable the entire Consent Decree, but raterh the entire Consent Decree shall be construed as if not
containing the particular unenforceable provision or provisions, and the rights and obligations of the
Parties shall be constuer d and enforced accordingly.
22. Invalidity. In the event that this Consent Decree in its entirety is rendered invalid by any
court of competent jurisdiction, it shall become null and void and may not be used in any manner in any
legal proceeding.
23. Subsequent Rule or Order. The Parties agree that if any provision of the Consent
Decree conflicts with any subsequent Rule or order adopted by the Commission (except an order
specifically intended to revise the terms of this Consent Decree to which FMBC does not expressly
consent) that provision will be superseded by such Rule or order.
24. Successors and Assigns. FMBC agrees that the provisions of this Consent Decree shall
be binding on its successors, assigns, and transfere es.
25. Final Settlement. The Parties agree and acknowledge that this Consent Decree shall
constitute a final settlement between the Parties with respect to the Investigation.
26. Modifications. This Consent Decree cannot be modified without the advance written
consent of both Parties.
27. Paragraph Headings. The headings of the paragraphs in this Consent Decree are
inserted for convenience only and are not intended to affect the meaning or interpretation of this Consent
Decree.
28. Authorized Representative. Each Party represents and warrants to the other that it has
full power and authority to enter into this Consent Decree. Each person signing this Consent Decree on
behalf of a Party hereby represents that he or she is fuly al uthorized by the Party to execute this Consent
Decree and to bind the Party to its terms and conditions.

24
See 5 U.S.C. S: 504; 47 CFR S:S: 1.1501-1.1530.
7
Federal Communications Commission DA 21-1365
29. Counterparts. This Consent Decree may be signedin c ounterpart (including
electronically or by facsimile). Each counterpart, when executed and diveelred, shall be an original, and
all of the counterparts together shall constitute one and the same fully executed instrument.


________________________________
Jeremy D. Marcus
Associate Chief
Enforcement Bureau


________________________________
Date



________________________________
Mark Gilson
AssistantS ecretary
Fort Myers Broadcasting Company

________________________________
Date
8