NOTICE
********************************************************
This document was converted from Microsoft Word.
Content from the original version of the document such as
headers, footers, footnotes, endnotes, graphics, and page numbers
will not show up in this text version.
All text attributes such as bold, italic, underlining, etc. from the
original document will not show up in this text version.
Features of the original document layout such as
columns, tables, line and letter spacing, pagination, and margins
will not be preserved in the text version.
If you need the complete document, download the
Microsoft Word or Adobe Acrobat version.
*****************************************************************
Federal Communications Commission DA 18-1079
Before the
Federal Communications Commission
Washington, DC 20554
In the Matter of )
)
San Isabel Telecom, Inc. ) File No.: EB-IHD-18-00026938
) Acct. No.: 201932080002
) FRN: 0005061775
ORDER
Adopted: November 14, 2018 Released: November 14, 2018
By the Chief, Enforcement Bureau:
1. The Enforcement Bureau (Bureau) of the Federal Communications Commission
(Commission) has entered into a Consent Decree to resolve its investigation into whether San Isabel
Telecom, Inc. (San Isabel) violated Section 214 of the Communications Act of 1934, as amended (Act)1,
and the Commission’s rules (Rules) related to the sale of assets to Futurum Communications Corp. d/b/a
Forethought.net (Futurum) prior to receiving approval from the Commission’s Wireline Competition and
International Bureaus. The Rules require prior approval to enable the Commission to apply a public
interest standard in evaluating possible risks to competition and consumers that could result from
transfers of substantial control of entities holding federally-granted authorizations pursuant to Section 214
of the Act. To settle this matter, San Isabel admits that it failed to obtain the Commission’s approval
prior to the sale of assets to Futurum, will implement a compliance plan, and will pay a $16,000
settlement amount.
2. After reviewing the terms of the Consent Decree and evaluating the facts before us, we
find that the public interest would be served by adopting the Consent Decree and terminating the
referenced investigation regarding San Isabel’s compliance with the Commission’s rules regarding the
requirement of prior Commission approval for the sale of assets as set forth in Section 214 of the Act2,
and Sections 63.03, 63.04, 63.18, and 63.24 of the Rules.3
3. In the absence of material new evidence relating to this matter, we do not set for hearing
the question of San Isabel’s basic qualifications to hold or obtain any Commission license or
authorization.4
5
4. Accordingly, IT IS ORDERED that, pursuant to Section 4(i) of the Act and the
authority delegated by Sections 0.111 and 0.311 of the Rules,6 the attached Consent Decree IS
ADOPTED and its terms incorporated by reference.
5. IT IS FURTHER ORDERED that the above-captioned matter IS TERMINATED.
1
47 U.S.C. § 214.
2
Id.
3
47 CFR §§ 63.03, 63.04, 63.18, 63.24.
4 See 47 CFR § 1.93(b).
5 47 U.S.C. § 154(i).
6 47 CFR §§ 0.111, 0.311.
Federal Communications Commission DA 18-1079
6. IT IS FURTHER ORDERED that a copy of this Order and Consent Decree shall be
sent by first class mail and certified mail, return receipt requested, to Jawaid Bazyar, Chief Executive
Officer, San Isabel Telecom, Inc., 2347 Curtis Street, Denver, CO 80205, and Lance J. M. Steinhart,
Counsel for San Isabel Telecom, Inc., 1725 Windward Concourse, Suite 150, Alpharetta, GA 30005.
FEDERAL COMMUNICATIONS COMMISSION
Rosemary C. Harold
Chief
Enforcement Bureau
2
Federal Communications Commission DA 18-1079
Before the
Federal Communications Commission
Washington, DC 20554
In the Matter of )
)
San Isabel Telecom, Inc. ) File No.: EB-IHD-18-00026938
) Acct. No.: 201932080002
) FRN: 0005061775
CONSENT DECREE
1. The Enforcement Bureau of the Federal Communications Commission and San Isabel
Telecom, Inc. (San Isabel), by their authorized representatives, hereby enter into this Consent Decree for
the purpose of terminating the Enforcement Bureau’s investigation, as defined below, into whether San
Isabel violated Section 214 of the Communications Act of 1934, as amended,1
and Sections 63.03, 63.04,
63.18, and 63.24 of the Commission’s rules,2
related to the sale of assets to Futurum Communications
Corp. d/b/a Forethought.net (Futurum) prior to receiving approval from the Commission’s Wireline
Competition and International Bureaus.3
I. DEFINITIONS
2. For the purposes of this Consent Decree, the following definitions shall apply:
(a) “Act” means the Communications Act of 1934, as amended.4
(b) “Adopting Order” means an order of the Bureau adopting the terms of this Consent
Decree without change, addition, deletion, or modification.
(c) “Bureau” means the Enforcement Bureau of the Federal Communications
Commission.
(d) “Commission” and “FCC” mean the Federal Communications Commission and all
of its bureaus and offices.
(e) “Communications Laws” means collectively, the Act, the Rules, and the published
and promulgated orders and decisions of the Commission to which San Isabel is
subject by virtue of its business activities, including but not limited to the Section
214 Rules.
(f) “Compliance Plan” means the compliance obligations, program, and procedures
described in this Consent Decree at paragraph 16.
(g) “Covered Employees” means all employees and agents of San Isabel who perform,
or supervise, oversee, or manage the performance of, duties that relate to San
Isabel’s responsibilities under the Communications Laws, including the Section 214
Rules.
1
47 U.S.C. § 214.
2
47 CFR §§ 63.03, 63.04, 63.18, 63.24.
3
See IBFS Application No. ITC-T/C-20180207-00029; Joint Application for Approval of Transfer of Control of
San Isabel Telecom Inc. to Futurum Communications Corp. d/b/a Forethought.net, WC Docket No. 18-50 (filed Jan.
30, 2018) (Joint Application).
4
47 U.S.C. § 151 et seq.
Federal Communications Commission DA 18-1079
(h) “Effective Date” means the date by which both the Bureau and San Isabel have
signed the Consent Decree.
(i) “Futurum” means Futurum Communications Corp d/b/a Forethought.net and its
affiliates, subsidiaries, predecessors-in-interest, and successors-in-interest.
(j) “Investigation” means the investigation commenced by the Bureau in EB-18-IHD-
00026938 regarding whether San Isabel violated the Section 214 Rules.
(k) “LOI” means the Letter of Inquiry issued by the Bureau to San Isabel on May 21,
2018 investigating whether San Isabel violated the Section 214 Rules related to the
transfer of control of the Company’s authorizations to provide domestic and
international service pursuant to Section 214 of the Act, prior to receiving approval
from the Commission’s Wireline Competition and International Bureaus.
(l) “Operating Procedures” means the standard internal operating procedures and
compliance policies established by San Isabel to implement the Compliance Plan.
(m) “Parties” means San Isabel and the Bureau, each of which is a “Party.”
(n) “Rules” means the Commission’s regulations found in Title 47 of the Code of
Federal Regulations.
(o) “San Isabel” or “Company” means San Isabel Telecom Inc. and its affiliates,
subsidiaries, predecessors-in-interest, and successors-in-interest.
(p) “Section 214 Rules” means Section 214 of the Act and other provisions of the Act,
the Rules, and Commission orders related to the construction, acquisition, operation,
or transmission of lines of communication, including any Rules implementing
Section 214 and any related Commission orders.
II. BACKGROUND
3. Section 214(a) of the Act requires telecommunications carriers to obtain a certificate of
public convenience and necessity from the Commission before constructing, acquiring, operating, or
engaging in the transmission of common carrier communications services over communications lines, and
before discontinuing, reducing, or impairing service to a community.5
The Commission granted all
carriers blanket authority under Section 214 to provide domestic interstate services and to construct,
acquire, or operate any domestic transmission line.6
In accordance with Section 63.03 of the Rules,
however, any domestic carrier seeking to transfer control of lines or authorization to operate pursuant to
Section 214 of the Act resulting from an acquisition of corporate control must obtain prior approval from
the Commission.7 The Commission has determined that transactions involving the sale of a
telecommunications provider’s customer base should be treated as transfers of control requiring
5
See 47 U.S.C. § 214(a).
6
47 CFR § 63.01; See Implementation of Section 402(b)(2)(A) of the Telecommunications Act of 1996; Petition for
Forbearance of the Independent Telephone & Telecommunications Alliance, Report and Order and Second
Memorandum Opinion and Order, 14 FCC Rcd 11364 (1999) (1999 Streamlining Order).
7
47 CFR § 63.03; See Implementation of Further Streamlining Measures for Domestic Section 214 Authorizatonsi ,
Report and Order, 17 FCC Rcd 5517, 5521, para. 5 (2002) (2002 Streamlining Order). See also 47 CFR
§ 63.03(d)(1) (excluding all pro forma transactions, which do not result in a change in the carrier’s ultimate
ownership or control, from the domestic Section 214 application and approval requirements), § 63.04(d)(2)
(requiring that a post-transaction notice be filed with the Commission within 30 days of a pro forma transfer of a
domestic Section 214 authorization to a trustee, a debtor-in-possession, or any other party pursuant to any applicable
chapter of the Bankruptcy Code).
2
Federal Communications Commission DA 18-1079
8
Commission approval. Section 63.04 sets forth the required contents of domestic transfer of control
applications.9
The Commission employs a public interest standard under Section 214(a) of the Act that
involves the examination of the public interest impact of a proposed transaction.10
4. While the Commission has granted “blanket” Section 214 authority to carriers providing
domestic service,11 meaning that such carriers need not apply to the Commission before providing
domestic service, the Commission has not done the same for providers of international
telecommunications services.12 Section 63.18 of the Rules requires any carrier that seeks Section 214
authority “for provision of common carrier communication services between the United States, its
territories or possessions, and a foreign point” to request such authority by application.13 This application
requirement applies to carriers that resell the international services of another authorized carrier, as well
as to facilities-based international service providers.14 In accordance with Section 63.24 of the Rules, an
international Section 214 authorization may be assigned, or control of such authorization may be
transferred by the transfer of control of any entity holding such authorization, to another party, whether
voluntarily or involuntarily, directly or indirectly, only upon application to and prior approval by the
Commission.15
5. San Isabel is a Colorado corporation providing competitive local exchange service, as
well as domestic and international interexchange and other services, to customers in Colorado.16 The
company also holds an international section 214 authority to provide resold international services.17 Until
December 19, 2016, the principal owner of San Isabel was Douglas Wagner.18
8
See 47 CFR §§ 63.01, 63.03, 63.04, 63.18 and 63.24; see also 2002 Streamlining Order, 17 FCC Rcd at 5547-49,
paras. 59-64 (modifying 47 CFR § 63.01 to reflect that asset purchases will no longer be subject to blanket authority,
but rather will be treated as transfers of control).
9
See 47 CFR § 63.04.
10 See 47 U.S.C. § 214(a).
11 47 CFR § 63.01(a) (“Any party that would be a domestic interstate communications common carrier is authorized
to provide domestic, interstate services to any domestic point and to construct or operate any domestic transmission
line as long as it obtains all necessary authorizations from the Commission for use of radio frequencies.”).
12 Implementation of Section 402(b)(2)(A) of the Telecomm. Act of 1996, Report and Order in CC Docket No. 97-11,
Second Memorandum Opinion & Order in AAD File No. 98-43, 14 FCC Rcd 11364, para. 2 & n.8 (1999) (grant of
blanket authority is only for domestic interstate services and does not extend to the provision of international
services).
13 47 CFR § 63.18.
14 Id. § 63.18(e)(1)-(2); see Start Wireless Group, Inc. d/b/a/ Page Plus Cellular, Notice of Apparent Liability for
Forfeiture, 27 FCC Rcd 350 (Enf. Bur. 2012).
15 47 CFR § 63.24(a.) “The sale of a customer base, or a portion of a customer base, by a carrier to another carrier,
is a sale of assets and shall be treated as an assignment which requires prior Commission approval under this
section.” 47 CFR § 63.24, Note to Paragraph (b).
16 Joint Application at 2; Joint Request for Special Temporary Authority to Operate Pending Approval of Transfer of
Control Application, WC Docket No. 18-50 (filed Feb. 8, 2018) and IBFS Application No. ITC-STA-20180208-
00032 (STA Request). See also Letter from Lance J.M. Steinhart, Counsel for San Isabel Telecom, Inc., to
Investigations & Hearings Div., Enforcement Bureau, Federal Communications Commission at 2 (July 5, 2018)
(LOI Response).
17 IBFS File No. ITC-214-20060320-00162.
18 STA Request at 3.
3
Federal Communications Commission DA 18-1079
6. Futurum is a Colorado corporation headquartered in Denver, Colorado, which uses the
trade name Forethought.net.19
Futurum also provides competitive local exchange and interexchange
20
telephone services and other services to customers in Colorado. Futurum did not hold any international
authorizations prior to December 19, 2016.21 Futurum is wholly owned by Jawaid Bazyar.22
7. On December 19, 2016, Forethought Acquisitions LLC, a wholly owned subsidiary of
Futurum, acquired all of the issued and outstanding stock in San Isabel (Transaction).23 At the time of the
Transaction, Futurum and its principals maintain that they “were not aware of the requirement for
Commission approval of the transaction.”24 As a result of the Transaction, San Isabel became a direct
wholly owned subsidiary of Forethought Acquisitions LLC, and an indirect wholly owned subsidiary of
Futurum.25 The Transaction resulted in transfers of control of the domestic and international section 214
authorizations held by San Isabel, and was completed without prior Commission consent.26 San Isabel
admits that neither Futurum nor San Isabel sought prior Commission approval for this transfer.27
8. On January 30, 2018, San Isabel and Futurum belatedly filed a joint transfer of control
application, pursuant to section 214 of the Act and sections 63.04 and 63.24 of the Commission’s rules,28
and a request for Special Temporary Authority (STA) with the International Bureau (IB) and the Wireline
Competition Bureau (WCB) on February 7 and 8, 2018, respectively.29 On February 22, 2018, WCB and
IB granted the applicants’ request for STA to allow San Isabel to operate while the proposed domestic
section 214 transfer of control application was under review.30 The underlying applications for approval
of the transfer of control were granted on March 29, 2018, by WCB, and March 23, 2018, by IB, without
prejudice to any enforcement action.31
19 Joint Application at 2; STA Request at 1.
20 Id.
21 Joint Application at 2-3.
22 STA Request at 4-5; LOI Response at 3.
23 STA Request at 1; LOI Response at 3.
24 STA Request at 2.
25 LOI Response at 4.
26 See International Authorizations Granted, Public Notice, Report No. TEL-01902 (IB Mar. 23, 2018)
(International 214 Grant PN).
27 See STA Request at 2; LOI Response at 6.
28
See generally Joint Application; 47 U.S.C. § 214; 47 CFR §§ 63.03-04. A copy of the Joint Application was filed
with WCB on February 20, 2018. See Domestic Section 214 Application Filed for the Transfer of Control of San
Isabel Telecom, Inc. to Futurum Communications Corp d/b/a Forethought.net, Public Notice, DA 18-184, WC
Docket No. 18-50 (WCB Feb. 26, 2018) (Domestic 214 PN).
29 See STA Request.
30 See Grant of San Isabel Telecom Inc. and Futurum Communications Corp. Joint Request for Special Temporary
Authority to Operate Pending Approval of Transfer of Control Application, WC Docket No. 18-50, File No. ITC-
STA-201 80208-00032 (Feb. 22, 2018).
31 Domestic Section 214 Authorization Granted, Public Notice, DA 18-316 (Mar. 29, 2018); International 214 Grant
PN.
4
Federal Communications Commission DA 18-1079
9. On May 21, 2018, the Bureau issued a Letter of Inquiry (LOI) regarding the matters
referenced above.32 33
On July 5, 2018, San Isabel filed its response to the LOI. The Parties negotiated the
following terms and conditions of settlement and hereby enter into this Consent Decree as provided
below.
III. TERMS OF AGREEMENT
10. Adopting Order. The provisions of this Consent Decree shall be incorporated by the
Bureau in an Adopting Order.
11. Jurisdiction. San Isabel agrees that the Bureau has jurisdiction over it and the matters
contained in this Consent Decree and has the authority to enter into and adopt this Consent Decree.
12. Effective Date; Violations. The Parties agree that this Consent Decree shall become
effective on the Effective Date as defined herein. As of the Effective Date, the Parties agree that this
Consent Decree shall have the same force and effect as any other order of the Commission.
13. Termination of Investigation. In express reliance on the covenants and representations
in this Consent Decree and to avoid further expenditure of public resources, the Bureau agrees to
terminate the Investigation. In consideration for the termination of the Investigation, San Isabel agrees to
the terms, conditions, and procedures contained herein. The Bureau further agrees that, in the absence of
new material evidence, it will not use the facts developed in the Investigation through the Effective Date,
or the existence of this Consent Decree, to institute, on its own motion, any new proceeding, formal or
informal, or take any action on its own motion against San Isabel concerning the matters that were the
subject of the Investigation. The Bureau also agrees that, in the absence of new material evidence, it will
not use the facts developed in the Investigation through the Effective Date, or the existence of this
Consent Decree, to institute on its own motion any proceeding, formal or informal, or to set for hearing
the question of San Isabel’s basic qualifications to be a Commission licensee or hold Commission
licenses or authorizations.34
14. Admission of Liability. San Isabel admits for the purpose of this Consent Decree and
for Commission civil enforcement purposes, and in express reliance on the provisions of paragraph 13
herein, that its actions described in paragraph 7, herein, violated the Section 214 Rules.
15. Compliance Officer. Within thirty (30) calendar days after the Effective Date, San
Isabel shall designate a senior corporate manager with the requisite corporate and organizational authority
to serve as a Compliance Officer and to discharge the duties set forth below. The person designated as
the Compliance Officer shall be responsible for developing, implementing, and administering the
Compliance Plan and ensuring that San Isabel complies with the terms and conditions of the Compliance
Plan and this Consent Decree. In addition to the general knowledge of the Communications Laws
necessary to discharge his or her duties under this Consent Decree, the Compliance Officer shall have
specific knowledge of the Section 214 Rules prior to assuming his/her duties.
16. Compliance Plan. For purposes of settling the matters set forth herein, San Isabel agrees
that it shall, within sixty (60) calendar days after the Effective Date, develop and implement a
Compliance Plan designed to ensure future compliance with the Communications Laws and with the
terms and conditions of this Consent Decree. With respect to the Section 214 Rules, San Isabel will
implement, at a minimum, the following procedures:
(a) Operating Procedures. Within thirty (30) calendar days after the Effective Date,
San Isabel shall establish Operating Procedures that all Covered Employees must
32 See Letter from Jeffrey J. Gee, Chief, Investigations and Hearings Division, FCC Enforcement Bureau, to Jawaid
Bazyar, Chief Executive Officer, San Isabel Telecom, Inc. (May 21, 2018) (on file in EB-18-IHD-00026938) (LOI).
33 See LOI Response.
34 See 47 CFR 1.93(b).
5
Federal Communications Commission DA 18-1079
follow to help ensure San Isabel’s compliance with the Section 214 Rules. In
addition to implementing the required policies and procedures in the Section 214
Rules, San Isabel’s Operating Procedures shall include internal procedures and
policies specifically designed to ensure that San Isabel complies with the Section
214 Rules. San Isabel shall also develop a Compliance Checklist that describes the
steps a Covered Employee must follow to ensure compliance with the Section 214
Rules.
(b) Compliance Manual. Within sixty (60) calendar days after the Effective Date, the
Compliance Officer shall develop and distribute a Compliance Manual to all
Covered Employees. The Compliance Manual shall explain Section 214 Rules and
set forth the Operating Procedures that Covered Employees shall follow to help
ensure San Isabel’s compliance with the Section 214 Rules. San Isabel shall
periodically review and revise the Compliance Manual as necessary to ensure that
the information set forth therein remains current and accurate. San Isabel shall
distribute any revisions to the Compliance Manual promptly to all Covered
Employees.
(c) Compliance Training Program. San Isabel shall establish and implement a
Compliance Training Program on compliance with the Section 214 Rules and the
Operating Procedures. As part of the Compliance Training Program, Covered
Employees shall be advised of San Isabel’s obligation to report any noncompliance
with the Section 214 Rules under paragraph 17 of this Consent Decree and shall be
instructed on how to disclose noncompliance to the Compliance Officer. All
Covered Employees shall be trained pursuant to the Compliance Training Program
within sixty (60) calendar days after the Effective Date, except that any person who
becomes a Covered Employee at any time after the initial Compliance Training
Program shall be trained within thirty (30) calendar days after the date such person
becomes a Covered Employee. San Isabel shall repeat compliance training on an
annual basis and shall periodically review and revise the Compliance Training
Program as necessary to ensure that it remains current and complete and to enhance
its effectiveness.
17. Reporting Noncompliance. San Isabel shall report any noncompliance with the Section
214 Rules and with the terms and conditions of this Consent Decree within fifteen (15) calendar days
after discovery of such noncompliance. Such reports shall include a detailed explanation of: (i) each
instance of noncompliance; (ii) the steps that San Isabel has taken or will take to remedy such
noncompliance; (iii) the schedule on which such remedial actions will be taken; and (iv) the steps that San
Isabel has taken or will take to prevent the recurrence of any such noncompliance. All reports of
noncompliance shall be submitted to the Chief, Investigations and Hearings Division, Enforcement
Bureau, Federal Communications Commission, 445 12th Street, SW Room 4-C224, Washington, DC
20554, with a copy submitted electronically to
Jeffrey.Gee@fcc.gov, Kalun.Lee@fcc.gov and to
Mindy.Littell@fcc.gov.
18. Compliance Reports. San Isabel shall file compliance reports with the Commission
ninety (90) calendar days after the Effective Date, twelve (12) months after the Effective Date and
twenty-four (24) months after the Effective Date.
(a) Each Compliance Report shall include a detailed description of San Isabel’s efforts
during the relevant period to comply with the terms and conditions of this Consent
Decree and the Section 214 Rules. In addition, each Compliance Report shall include
a certification by the Compliance Officer, as an agent of and on behalf of San Isabel,
stating that the Compliance Officer has personal knowledge that San Isabel: (i) has
established and implemented the Compliance Plan; (ii) has utilized the Operating
Procedures since the implementation of the Compliance Plan; and (iii) is not aware of
6
Federal Communications Commission DA 18-1079
any instances of noncompliance with the terms and conditions of this Consent
Decree, including the reporting obligations set forth in paragraph 17 of this Consent
Decree.
(b) The Compliance Officer’s certification shall be accompanied by a statement
explaining the basis for such certification and shall comply with Section 1.16 of the
Rules and be subscribed to as true under penalty of perjury in substantially the form
set forth therein.35
(c) If the Compliance Officer cannot provide the requisite certification, the Compliance
Officer, as an agent of and on behalf of San Isabel, shall provide the Commission
with a detailed explanation of the reason(s) why and describe fully: (i) each instance
of noncompliance; (ii) the steps that San Isabel has taken or will take to remedy such
noncompliance, including the schedule on which proposed remedial actions will be
taken; and (iii) the steps that San Isabel has taken or will take to prevent the
recurrence of any such noncompliance, including the schedule on which such
preventive action will be taken.
(d) All Compliance Reports shall be submitted the Chief, Investigations and Hearings
Division, Enforcement Bureau, Federal Communications Commission, 445 12th
Street, SW Room 4-C224, Washington, DC 20554, with a copy submitted
electronically to Jeffrey.Gee@fcc.gov, Kalun.Lee@fcc.gov and to
Mindy.Littell@fcc.gov.
19. Termination Date. Unless stated otherwise, the requirements set forth in paragraphs 15
through 18 of this Consent Decree shall expire twenty-four (24) months after the Effective Date.
20. Section 208 Complaints; Subsequent Investigations. Nothing in this Consent Decree
shall prevent the Commission or its delegated authority from adjudicating complaints filed pursuant to
Section 208 of the Act36 against San Isabel or its affiliates for alleged violations of the Act, or for any
other type of alleged misconduct, regardless of when such misconduct took place. The Commission’s
adjudication of any such complaint will be based solely on the record developed in that proceeding.
Except as expressly provided in this Consent Decree, this Consent Decree shall not prevent the
Commission from investigating new evidence of noncompliance by San Isabel with the Communications
Laws.
21. Settlement Amount. San Isabel will make a settlement payment to the United States
Treasury in the amount of sixteen thousand dollars ($16,000). Such payment shall be made in twelve (12)
installments (each an Installment Payment). The first Installment Payment in the amount of One
Thousand Three Hundred Thirty-Seven Dollars ($1,337) is due on December 1, 2018. Thereafter,
subsequent Installment Payments of One Thousand Three Hundred Thirty-Seven Dollars ($1,333) will be
due on the first day of each month with the final payment due on the first day of the twelfth month
following the Effective Date. San Isabel acknowledges and agrees that upon execution of this Consent
Decree, the civil penalty and each Installment Payment shall become a “Claim” or “Debt” as defined in
31 U.S.C. § 3701(b)(1).37 Upon an Event of Default (as defined below), all procedures for collection as
permitted by law may, at the Commission’s discretion, be initiated.
San Isabel shall send electronic notification of payment to the Chief, Investigations and Hearings
Division, Enforcement Bureau, Federal Communications Commission, 445 12th Street, SW Room 4-
C224, Washington, DC 20554, with a copy submitted electronically to Jeffrey.Gee@fcc.gov,
35 47 CFR § 1.16.
36 47 U.S.C. § 208.
37 Debt Collection Improvement Act of 1996, Pub. L. No. 104-134, 110 Stat. 1321, 1358 (Apr. 26, 1996).
7
Federal Communications Commission DA 18-1079
Kalun.Lee@fcc.gov and to Mindy.Littell@fcc.gov on the date said payment is made. The payment must
be made by check or similar instrument, wire transfer, or credit card, and must include the Account
Number and FRN referenced above. Regardless of the form of payment, a completed FCC Form 159
(Remittance Advice) must be submitted.38 When completing the FCC Form 159, enter the Account
Number in block number 23A (call sign/other ID) and enter the letters “FORF” in block number 24A
(payment type code). Below are additional instructions that should be followed based on the form of
payment selected:
Payment by check or money order must be made payable to the order of the Federal
Communications Commission. Such payments (along with the completed Form 159) must be
mailed to Federal Communications Commission, P.O. Box 979088, St. Louis, MO 63197-
9000, or sent via overnight mail to U.S. Bank – Government Lockbox #979088,
SL-MO-C2-GL, 1005 Convention Plaza, St. Louis, MO 63101.
Payment by wire transfer must be made to ABA Number 021030004, receiving bank
TREAS/NYC, and Account Number 27000001. To complete the wire transfer and ensure
appropriate crediting of the wired funds, a completed Form 159 must be faxed to U.S. Bank
at (314) 418-4232 on the same business day the wire transfer is initiated.
Payment by credit card must be made by providing the required credit card information on
FCC Form 159 and signing and dating the Form 159 to authorize the credit card payment.
The completed Form 159 must then be mailed to Federal Communications Commission, P.O.
Box 979088, St. Louis, MO 63197-9000, or sent via overnight mail to U.S. Bank –
Government Lockbox #979088, SL-MO-C2-GL, 1005 Convention Plaza, St. Louis, MO
63101.
Questions regarding payment procedures should be addressed to the Financial Operations Group
ARINQUIRIES@fcc.gov
Help Desk by phone, 1-877-480-3201, or by e-mail, .
22. Event of Default. San Isabel agrees that an Event of Default shall occur upon the failure
by San Isabel to pay the full amount of any Installment Payment on or before the due date specified in this
Consent Decree.
23. Interest, Charges for Collection, and Acceleration of Maturity Date. After an Event
of Default has occurred under this Consent Decree, the then unpaid amount of the civil penalty shall
accrue interest, computed using the U.S. Prime Rate in effect on the date of the Event of Default plus 4.75
percent, from the date of the Event of Default until payment in full. Upon an Event of Default, the then
unpaid amount of the civil penalty, together with interest, any penalties permitted and/or required by the
law, including but not limited to 31 U.S.C. § 3717 and administrative charges, plus the costs of collection,
litigation, and attorneys’ fees, shall become immediately due and payable, without notice, presentment,
demand, protest, or notice of protest of any kind, all of which are waived by San Isabel.
24. Waivers. As of the Effective Date, San Isabel waives any and all rights it may have to
seek administrative or judicial reconsideration, review, appeal or stay, or to otherwise challenge or contest
the validity of this Consent Decree and the Adopting Order. San Isabel shall retain the right to challenge
Commission interpretation of the Consent Decree or any terms contained herein. If either Party (or the
United States on behalf of the Commission) brings a judicial action to enforce the terms of the Consent
Decree or the Adopting Order, neither San Isabel nor the Commission shall contest the validity of the
Consent Decree or the Adopting Order, and San Isabel shall waive any statutory right to a trial de novo.
San Isabel hereby agrees to waive any claims it may otherwise have under the Equal Access to Justice
Act39 relating to the matters addressed in this Consent Decree.
38 An FCC Form 159 and detailed instructions for completing the form may be obtained at
http://www.fcc.gov/Forms/Form159/159.pdf.
39 See 5 U.S.C. § 504; 47 CFR §§ 1.1501–1.1530.
8
Federal Communications Commission DA 18-1079
25. Severability. The Parties agree that if any of the provisions of the Consent Decree shall
be held unenforceable by any court of competent jurisdiction, such unenforceability shall not render
unenforceable the entire Consent Decree, but rather the entire Consent Decree shall be construed as if not
containing the particular unenforceable provision or provisions, and the rights and obligations of the
Parties shall be construed and enforced accordingly.
26. Invalidity. In the event that this Consent Decree in its entirety is rendered invalid by any
court of competent jurisdiction, it shall become null and void and may not be used in any manner in any
legal proceeding.
27. Subsequent Rule or Order. The Parties agree that if any provision of the Consent
Decree conflicts with any subsequent Rule or Order adopted by the Commission (except an Order
specifically intended to revise the terms of this Consent Decree to which San Isabel does not expressly
consent) that provision will be superseded by such Rule or Order.
28. Successors and Assigns. San Isabel agrees that the provisions of this Consent Decree
shall be binding on its successors, assigns, and transferees.
29. Final Settlement. The Parties agree and acknowledge that this Consent Decree shall
constitute a final settlement between the Parties with respect to the Investigation.
30. Modifications. This Consent Decree cannot be modified without the advance written
consent of both Parties.
31. Paragraph Headings. The headings of the paragraphs in this Consent Decree are
inserted for convenience only and are not intended to affect the meaning or interpretation of this Consent
Decree.
32. Authorized Representative. Each Party represents and warrants to the other that it has
full power and authority to enter into this Consent Decree. Each person signing this Consent Decree on
behalf of a Party hereby represents that he or she is fully authorized by the Party to execute this Consent
Decree and to bind the Party to its terms and conditions.
33. Counterparts. This Consent Decree may be signed in counterpart (including
electronically or by facsimile). Each counterpart, when executed and delivered, shall be an original, and
all of the counterparts together shall constitute one and the same fully executed instrument.
________________________________
Rosemary C. Harold
Chief
Enforcement Bureau
________________________________
Date
________________________________
Jawaid Bazyar
Chief Executive Officer
San Isabel Telecom, Inc.
________________________________
Date
9